October 6 - 10

Various trades will be working on site this week including work commencing on sewer on the east side of the building and steel installation. The drawing below indicates areas that will be restricted access. NOTE: Restrictions will likely change throughout the week so please follow signage and fencing at all times.

Please continue to use the front door for primary egress. W4 and E4 will remain available for emergency exit only.