Week of December 9 -15

The past month has been somewhat unpredictable due to subcontractor availability.

Next week there is a plan in place to remove and replace the human door (W4) next to the loading dock. We are estimated this work will take between three to four days. During this time this door will not be open for egress. Please make note of the plan below and continue to use the front door for entering the building.

The loading dock will remain open.

Door E4 on the east side of the building is open again but please proceed with caution. This side of the building remains closed for parking until further notice.