Week of July 15 - 21
We will be commencing work on filling in the holes created from the micropile work with concrete this week. This process involves building rebar cages first, lowering them into the holes, followed by a concrete pour. The plan is to do this work in defined areas of the building starting with the area near the freight elevator outside Saxy, Jacks and Stems on Tuesday. The construction crew will be fencing off the area in the interior of the building that will define clear paths for egress. Please continue to use the front door for entering and exiting the building.