Weeks of March 11-22
EGRESS PLAN: WEEKS OF MARCH 11-22,2023
WEEK OF 3/11-3/15
The east side of the building will remain closed for entry within the construction fenced off area. Please note that E4 and E5 are for EMERGENCY EXITS ONLY. An emergency constitutes a life threatening situation, not forgetting something in your car for example.
The west side of the building will remain open from Monday, March 11th - Friday, March 15th.
NOTE: There may be part of a day that the west entrance by the loading dock (W4) will be unavailable. To avoid confusion around periodic closures it would be best to get in the habit of using the main entrance. This is the safest and easiest option for communication with customers coming to your business.
WEEK OF 3/18-3/22
We will be driving piles on the west side of the building during this week and the west entrance (W4) will be off limits for one or two days. We will notify you of those dates as soon as we know. Construction fencing will be put in place. We ask that you remain mindful of this and not go into the construction area.
Egress on the east side of the building will remain the same as the week of 3/11-3/15.